Home || Landscapes || Water Features || Pools & Spas || Perennial Gardens || Annual Flower Displays  || Landscape Lighting
Outdoor Living || Pavements & Walls || Special Landscape Features || Storm Water Management || Parks & Zoos
About || Design Service || Awards || Residential || Commercial || Site Analysis || Waste Water Management  || Presentations

Designscapes, Inc.

Award-Winning Landscape Design in Michigan

FRANKENMUTH RIVER PLACE

As in most commercial developments, hardscape design is of key importance.  It’s the hardscape that sets up the circulation pattern for guests, bringing them to each shop in the development.  FRANKENMUTH RIVER PLACE was no exception in this regard.  Water features were constructed to create the ‘River Place’ theme on this site as well as help to guide pedestrians through this ‘European Village’ shopping center.  In addition, we had to provide access to both public and private boat docks located on the Cass River. 

THE GARDEN POND DESIGN:  This water feature is part of the entry courtyard garden.  It is a small waterfall spilling into a quiet pond.  The challenge here was that a bridge had to be constructed over the pond.  The bridge design required a continuous footing through the pond area.  There were three arches placed on this footing to create the bridge over the water.  Because the liner had to be completely concealed, there was no good way to run the liner through these arches. 

The best option appeared to be to build the bridge on top of the liner.  Our concerns were properly sequencing the construction and preventing punctures of the liner.  To make construction even more difficult, the bridge had to be useable within one week from the start of excavation, because this was a primary access point to the site.

THE CENTRAL STREAM DESIGN:  The original concept that the architect had was to construct a low barrier wall along the walkways adjacent to the stream to keep people away from the water.  Our vision was to keep the water and landscape accessible so guests could enjoy it more fully.  Fortunately, our vision for this area prevailed. 

There were several benefits to eliminating the barrier walls.  One was being able to direct rainwater flows from the sidewalks into the stream.  This saved the expense of installing catch basins and drains in the sidewalks.  A second benefit was creating a more natural look to the entire stream and sidewalk area.  Since the sidewalks were all heated, there was no worry about de-icing salts flowing into the stream or pond.  We also eliminated the expense of an irrigation system by constructing the landscape on top of the liner.

THE MAIN WATERFALL DESIGN:  When pedestrians approach this site from the north, they cross the Cass River via a new bridge.  At the end of this bridge, guests are greeted by the thundering flow of 2400 gallons per minute dropping down a twenty foot high, eighty foot long rapids to the Cass River.  Combined with the Cass River, it provides the visual statement for the ‘Frankenmuth River Place’ theme.

On this part of the project, we faced numerous challenges.  First was the budget.  The original approach was to construct the waterfall with steel reinforced concrete.   As the design progressed, the cost estimates kept getting higher   We finally scrapped the concept calling for concrete, and went to an EPDM liner covered with large (up to five by seven feet) stone slabs.

Second, we had to allow for the potential flooding of the Cass River.  On previous occasions, the flood level has been as much as eighteen feet above normal water levels.  To maximize the ability of this water feature to handle flood waters, massive pieces (up to four tons each) of limestone were used during construction.  To support all this weight, we started with a steel sheet piling driven in at the edge of the river.  This allowed a concrete footing to be poured behind the sheet piling and below the water level of the river.   

Third, the effect that we wanted to create required a flow rate of 2400 gallons per minute at 20 feet of vertical head.  This meant two submersible pumps, fifteen horsepower each, had to hidden somewhere.  We designed a pump well with an access hatch into the new boat dock that was being installed adjacent to the base of the waterfall.  From this well, two 10” diameter pipes carried the river water to the top of the waterfall.

With that much water, we had to have a way to disperse the flow at the top of the waterfall or it would look like it was shooting out of a pipe instead of flowing out from under the simulated bridge.  This was accomplished by pouring the "bridge" abutments and foundation to create a dispersal tank.  As the water flows into the bottom of this tank, the velocity drops.  By the time it flows out the top of this tank, it looks like a continuation of the stream from the other side of the "bridge."

CONCLUSION:  The construction schedule for landscape and hardscape on this project was compressed to two months.  This meant having three landscape contractors, two excavating contractors, and an irrigation contractor on site at the same time.  In addition, the interiors and exteriors of the buildings were still under construction.  This meant a high degree of cooperation from all the trades working on the site.  It also meant a great deal of prior planning on our part.

All the pavement elevations and drainage patterns had to be determined in conjunction with designing the water features.  The limited spaces created tight tolerances, and required a great deal of site supervision to execute.  All the planning paid off in the finished project. 

The combination of architecture and special features make guests feel they are in a real European village.  The infrastructure is well hidden and operates with minimal headaches.  As a result, business is good and the owners and tenants are happy.  We faced a lot of challenges with this project, but I’m proud to have been involved.


Landscapes || Water Features || Pools & Spas || Perennial Gardens || Annual Flower Displays  || Landscape Lighting
Outdoor Living || Pavements & Walls || Special Landscape Features || Storm Water Management || Parks & Zoos
About Designscapes, Inc.|| Our Landscape Design Service || Waste Water Management

Designscapes, Inc.
Landscape Architecture & Project Management
659 Zehnder Drive
Frankenmuth, Michigan 48734
phone 989-652-4981   fax 989-652-4982
dscapes@dscapes.com